Hazard Mitigation Plan - Mitigation Actions Database

New York City’s comprehensive effort to reduce or eliminate potential losses from the hazards described in the Hazard Specific section of the website. The map includes existing and completed mitigation actions that will minimize the effects of a hazard event on New York City’s population, economy, property, building stock, and infrastructure. It is the result of a coordinated effort by 46 New York City agencies and partners to develop and implement a broad range of inventive and effective ways to mitigate hazards.

NOTE: This table can be joined to the mapped projects using the HMP Index field.
For the Hazard Mitigation Plan map, please follow this link: https://data.cityofnewyork.us/d/n6jh-qsrw

Spatial data for projects that were mapped is available here:
Points: https://data.cityofnewyork.us/City-Government/New-York-City-Emergency-Management-Points-/t7k8-wj6b
Lines: https://data.cityofnewyork.us/City-Government/Hazard-Mitigation-Plan-Mitigation-Actions-Database/hqhh-iv7p
Polygons: https://data.cityofnewyork.us/City-Government/Hazard-Mitigation-Plan-Mitigation-Actions-Database/cj2p-e3ej

City Government NYC Emergency Management (NYCEM) Dataset veqt-eu3t 28 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
MA.00265
Hmp Index: MA.00265 • Mitigation Actions Title: Climate and health community resilience • Lead Agency: Department of Health and Mental Hygiene
Hmp Index
MA.00265
Mitigation Actions Title
Climate and health community resilience
Mitigation Actions Description
Conduct workshops and disseminate public health information and educational tools through community stakeholders, professional associations, faith-based coalitions, and agencies that provide services to vulnerable populations (children, seniors, inmates, the homeless, and the mentally ill). Workshops provide instruction on how to reduce illness and mortality associated with extreme weather
Lead Agency
Department of Health and Mental Hygiene
Action Category
Public Education and Awareness
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,High Winds
Other Funding Source
Other
Contact Name
Office of Emergency Preparedness and Response
Contact Email
emergencyprep@health.nyc.gov
Notes
Ongoing
MA.00266
Hmp Index: MA.00266 • Mitigation Actions Title: Environment and Health Data Portal • Lead Agency: Department of Health and Mental Hygiene
Hmp Index
MA.00266
Mitigation Actions Title
Environment and Health Data Portal
Mitigation Actions Description
Facilitate environmental data dissemination to the public using web-based data systems. Data dissemination supports community preparedness, public education, and characterization of potential environmental hazards.
Lead Agency
Department of Health and Mental Hygiene
Action Category
Public Education and Awareness
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality
Estimated Cost
$753,000.00
City Funding Source
City Expense
Other Funding Source
Other
Description Of Social Vulnerability Addressed
Releases data and information with a health equity analysis - ways that inequality is a public health problem.
Administrative Technical Capability
Yes
Education Outreach Capability
Yes
Contact Name
Office of Emergency Preparedness and Response
Contact Email
emergencyprep@health.nyc.gov
Web Link
https://a816-dohbesp.nyc.gov/IndicatorPublic/beta/
MA.00267
Hmp Index: MA.00267 • Mitigation Actions Title: Assessing and communicating risks from drinking and recreational waters • Lead Agency: Department of Health and Mental Hygiene
Hmp Index
MA.00267
Mitigation Actions Title
Assessing and communicating risks from drinking and recreational waters
Mitigation Actions Description
Issue public advisories on health hazards from flooding/storm impacts to water supply and public waters/beaches, using 311, nyc.gov, printed materials and media.
Description Problem
Water quality can be impacted by bacteria, floatable debris, animal waste, medical or infectious waste, toxic contaminants, petroleum products, sewage, and wastewater discharge following heavy rainfall. DOHMH monitors permitted beaches in NYC and provides notification when the water has high levles of bacteria
Lead Agency
Department of Health and Mental Hygiene
Action Category
Public Education and Awareness
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
City Funding Source
City Expense
Contact Name
Office of Public Health Engineering
Contact Email
PHE@health.nyc.gov
Notes
Ongoing https://a816-dohbesp.nyc.gov/IndicatorPublic/Beaches/
MA.00268
Hmp Index: MA.00268 • Mitigation Actions Title: 3-D Mapping Underground Project • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00268
Mitigation Actions Title
3-D Mapping Underground Project
Mitigation Actions Description
The 3-D Underground project is intended to collect and make available in an integrated way the data sets which describe the infrastructure features present beneath the streets of NYC. Bringing all the data together would shorten the time needed to integrate data in those instances, but also allow more comprehensive planning for budgeting capital construction, for targeting areas of concern regarding public safety, and for comprehensive resiliency planning as the Citys infrastructure ages.
Lead Agency
Office of Technology and Innovation
Support Agency
Mayors Office of Operations,New York City Emergency Management
Action Category
Prevention and Policy
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Non-Natural
Estimated Start
2023-06-01T00:00:00.000
Estimated Finish
2027-08-31T00:00:00.000
Estimated Cost
$10,000,000.00
Federal Funding Source
HUD CDBG
Description Of Critical Facility
Prevention of damage to critical facility infrastructure (e.g., Fresh Water Tanks / Facilities)
Planning Regulation Capability
Improve capital construction planning and help prevent new / major construction projects from damaging critical City infrastructure
Administrative Technical Capability
Digitally provide accurate location of critical City infrastructure under the streets
Financial Capability
Improve forecasting and estimation of large capital projects
MA.00270
Hmp Index: MA.00270 • Mitigation Actions Title: Citywide VOIP • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00270
Mitigation Actions Title
Citywide VOIP
Mitigation Actions Description
Allow users to move to a different location with minimal reconfiguration and have regular phone numbers restored within hours if a City office building becomes inaccessible due to severe impact to both the PBX and Centrex lines.
Lead Agency
Office of Technology and Innovation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural
Estimated Start
2014-08-31T00:00:00.000
Estimated Cost
$10,000,000.00
City Funding Source
City Capital
MA.00271
Hmp Index: MA.00271 • Mitigation Actions Title: Session Initiation Protocol (SIP) • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00271
Mitigation Actions Title
Session Initiation Protocol (SIP)
Mitigation Actions Description
Implement SIP for voice communication between 311 and the carrier's public network, enabling the City to be less reliant on one carrier central office and have the ability to fail over to alternate locations.
Lead Agency
Office of Technology and Innovation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural
Estimated Cost
$3,500,000.00
City Funding Source
City Capital
MA.00273
Hmp Index: MA.00273 • Mitigation Actions Title: IP routing network • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00273
Mitigation Actions Title
IP routing network
Mitigation Actions Description
Harden the network, providing the City with required advanced bandwidth management devices to regulate appropriate use of ISP links during emergencies.
Lead Agency
Office of Technology and Innovation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural
Estimated Start
2016-10-02T00:00:00.000
Estimated Finish
2017-10-01T00:00:00.000
Estimated Cost
$2,900,000.00
City Funding Source
City Capital
Notes
The network has been hardened with the industry leading BGP routing protocol and the Internet bandwidth is being upgraded to 40 Gbps.
MA.00274
Hmp Index: MA.00274 • Mitigation Actions Title: 311 upgrade • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00274
Mitigation Actions Title
311 upgrade
Mitigation Actions Description
Support future high-call-volume events including re-architecture of the 311 platform, provide production environment for call center-specific version of applications, and implement cloud-based mapping.
Lead Agency
Office of Technology and Innovation
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Disease Outbreak,Non-Natural
Estimated Cost
$29,000,000.00
City Funding Source
City Capital
MA.00275
Hmp Index: MA.00275 • Mitigation Actions Title: 311 alternate site • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00275
Mitigation Actions Title
311 alternate site
Mitigation Actions Description
Build out an operating environment in a hardened facility to insure that 311 operations can relocate to an alternate site should primary facility be impacted.
Lead Agency
Office of Technology and Innovation
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Disease Outbreak,Non-Natural
Estimated Cost
$13,000,000.00
Other Funding Source
Unknown
MA.00276
Hmp Index: MA.00276 • Mitigation Actions Title: Hardening the optical backbone • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00276
Mitigation Actions Title
Hardening the optical backbone
Mitigation Actions Description
Implement new omni-directional optical technology to enable DoITT to remotely switch the light and route traffic around failed fiber path. Citynet, the City's dedicated optical fiber backbone, is already undergoing a significant upgrade to increase its capacity and resiliency. While the network has the ability to dynamically switch the IP at the ethernet layer, it does not have ability to remotely switch the light through multiple fiber paths during emergencies.
Lead Agency
Office of Technology and Innovation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Non-Natural
Estimated Cost
$17,000,000.00
Other Funding Source
Unknown
MA.00277
Hmp Index: MA.00277 • Mitigation Actions Title: Internet/DMZ management • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00277
Mitigation Actions Title
Internet/DMZ management
Mitigation Actions Description
Sustain advanced bandwidth management devices to regulate appropriate usage of ISP links during emergencies.
Lead Agency
Office of Technology and Innovation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Disease Outbreak,Non-Natural
Estimated Start
2013-12-31T00:00:00.000
Estimated Finish
2014-06-01T00:00:00.000
Estimated Cost
$1,550,000.00
City Funding Source
City Capital
MA.00278
Hmp Index: MA.00278 • Mitigation Actions Title: Hardening of the NYC wireless network (NYCWiN) network • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00278
Mitigation Actions Title
Hardening of the NYC wireless network (NYCWiN) network
Mitigation Actions Description
Install fixed generators at 126 NYCWiN sites to protect and enhance the reliability and resiliency of communications infrastructure.
Lead Agency
Office of Technology and Innovation
Action Category
Infrastructure Projects
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Non-Natural
Estimated Cost
$11,200,000.00
Federal Funding Source
FEMA
Notes
Project was never funded as NYCWiN was designated to be decomissioned by June of 2019
MA.00279
Hmp Index: MA.00279 • Mitigation Actions Title: Data Center Site B • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00279
Mitigation Actions Title
Data Center Site B
Mitigation Actions Description
Provide consolidated Site B capability and capacity for applications not already hosted at DoITT's 2 MTC Data Center.
Lead Agency
Office of Technology and Innovation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Start
2012-12-31T00:00:00.000
Estimated Cost
$50,000,000.00
City Funding Source
City Capital
Other Funding Source
Unknown
MA.00280
Hmp Index: MA.00280 • Mitigation Actions Title: Telecomm facility hardening across 40 locations • Lead Agency: Office of Technology and Innovation
Hmp Index
MA.00280
Mitigation Actions Title
Telecomm facility hardening across 40 locations
Mitigation Actions Description
Project is necessary to harden telecomm facilities to across Citynet sites. Initiative will improve air handling, and power utilization
Description Problem
Facilities are operating with antiquated solutions. May components are beyond repair. Some sites also present safety issues as well
Lead Agency
Office of Technology and Innovation
Action Category
Infrastructure Projects
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Earthquakes,Flooding,High Winds,Non-Natural,#Energy saving
Estimated Cost
$60,000,000.00
City Funding Source
City Capital
Notes
Project costs have been pushed several times. FY30 seems to be the earliest start
MA.00281
Hmp Index: MA.00281 • Mitigation Actions Title: Palo Alto Firewall • Lead Agency: Department of Investigation
Hmp Index
MA.00281
Mitigation Actions Title
Palo Alto Firewall
Mitigation Actions Description
DOI will use Palo Alto's next-generation firewalls to detect known and unknown threats, in regular and encrypted network traffic to reduce risks and prevent a wide range of cyber-security attacks. The new firewalls will improve DOI's security posture by substantially decreasing attack vectors that malicious and unaware actors might try to use to exploit vulnerabilities in systems used by the Agency.
Lead Agency
Department of Investigation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural
Estimated Start
2017-12-31T00:00:00.000
Estimated Finish
2019-01-30T00:00:00.000
Estimated Cost
$2,200,000.00
City Funding Source
City Capital
Description Of Critical Facility
Disaster recovery
MA.00282
Hmp Index: MA.00282 • Mitigation Actions Title: Cisco ISE • Lead Agency: Department of Investigation
Hmp Index
MA.00282
Mitigation Actions Title
Cisco ISE
Mitigation Actions Description
Cisco ISE or Identity Services Engine is a network administration system that facilitates the establishment and enforcement of security and policies for endpoint devices connected to the agency's network. ISE will also simplify managing identities for a variety of appliances, devices, and applications.
Lead Agency
Department of Investigation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural
Estimated Start
2018-01-09T00:00:00.000
Estimated Finish
2019-01-30T00:00:00.000
Estimated Cost
$160,000.00
City Funding Source
City Capital
MA.00284
Hmp Index: MA.00284 • Mitigation Actions Title: Disaster Recovery Site Hardware Upgrade • Lead Agency: Department of Investigation
Hmp Index
MA.00284
Mitigation Actions Title
Disaster Recovery Site Hardware Upgrade
Mitigation Actions Description
The upgrade of the hardware and software at the disaster recovery site will expand DOI's capabilities to protect the agency's systems against the effects of significant negative events. The upgraded DR site will allow the organization to maintain and resume quickly mission-critical functions following any disaster, including cyber-attacks, equipment failures, and natural disasters.
Lead Agency
Department of Investigation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Start
2018-01-09T00:00:00.000
Estimated Finish
2019-01-30T00:00:00.000
Estimated Cost
$4,500,000.00
City Funding Source
City Capital
Description Of Critical Facility
Disaster Recovery Site
MA.00285
Hmp Index: MA.00285 • Mitigation Actions Title: Backup software/hardware updgrade • Lead Agency: Department of Investigation
Hmp Index
MA.00285
Mitigation Actions Title
Backup software/hardware updgrade
Mitigation Actions Description
The backup system upgrade will provide the ability to continue protecting DOI's data and systems by providing the necessary capacity and capability to recover data after loss, deletion or corruption.
Lead Agency
Department of Investigation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,High Winds,Non-Natural
Estimated Start
2018-01-09T00:00:00.000
Estimated Finish
2019-01-30T00:00:00.000
Estimated Cost
$2,000,000.00
City Funding Source
City Capital
Description Of Critical Facility
Disaster Recovery Site and Production Site
MA.00286
Hmp Index: MA.00286 • Mitigation Actions Title: Citrix VDI • Lead Agency: Department of Investigation
Hmp Index
MA.00286
Mitigation Actions Title
Citrix VDI
Mitigation Actions Description
Citrix VDI or Virtual Desktop Infrastructure enables the creation of virtual desktops allowing users access to all the organization's software applications and data in a controlled environment. VDI provides control of software configuration in every virtual desktop that includes the latest patches and security updates. Also, sensitive data never leaves the data center, where data is audited and protected against theft.
Lead Agency
Department of Investigation
Action Category
Infrastructure Projects
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Non-Natural,Disease Outbreak,Poor Air Quality
Estimated Start
2020-07-22T00:00:00.000
Estimated Finish
2020-10-15T00:00:00.000
Estimated Cost
$109,691.28
Other Funding Source
DOI
Description Of Critical Facility
Production Site
MA.00287
Hmp Index: MA.00287 • Mitigation Actions Title: Beach restoration • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00287
Mitigation Actions Title
Beach restoration
Mitigation Actions Description
Reconstruct dunes and shoreline protection in DPR beaches damaged by Hurricane Sandy.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms
Estimated Cost
$52,000,000.00
Administrative Technical Capability
Natural Resources Group
MA.00289
Hmp Index: MA.00289 • Mitigation Actions Title: Orchard Beach, NY Project • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00289
Mitigation Actions Title
Orchard Beach, NY Project
Mitigation Actions Description
The project includes the placement of 268,000 cubic yards of beachfill and nearly 4,000 tons of stone for groin rehabilitation. (USACE classifies this project as "Recreational" and not flood damage reduction.)
Lead Agency
Department of Parks and Recreation
Support Agency
U.S. Army Corps of Engineers
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion
Estimated Start
2009-12-31T00:00:00.000
Estimated Finish
2011-05-30T00:00:00.000
Estimated Cost
$12,000,000.00
Federal Funding Source
USACE
Web Link
http://www.nan.usace.army.mil/Media/Fact-Sheets/Fact-Sheet-Article-View/Article/487413/fact-sheet-orchard-beach/
Notes
Nourishment cycle dependent on project surveys and available funding
MA.00290
Hmp Index: MA.00290 • Mitigation Actions Title: NYC Parks Tottenville Shoreline Protection Project • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00290
Mitigation Actions Title
NYC Parks Tottenville Shoreline Protection Project
Mitigation Actions Description
The proposed project utilizes almost entirely nature-based solutions including an earthen berm, hybrid dune, eco-revetments in areas where the beach width is limited, green infrastructure, and a restored wetland. The project was designed to mitigate the wave impacts of a 25-year storm event and evaluated considering future conditions including SLR to the year- 2080. The project was designed assuming a 50-year or greater design life.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding,Coastal Erosion
Estimated Cost
$26,345,767.00
Federal Funding Source
FEMA-BRIC
Planning Regulation Capability
Flood Resiliency Guidelines
Administrative Technical Capability
Floodplain Maps/Flood Insurance Studies – NFIP Compliance,Resiliency Planning Staff
Notes
4 years duration
MA.00291
Hmp Index: MA.00291 • Mitigation Actions Title: Sunset Cove Parks sustainable shoreline at Broad Channel, Jamaica Bay • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00291
Mitigation Actions Title
Sunset Cove Parks sustainable shoreline at Broad Channel, Jamaica Bay
Mitigation Actions Description
Construct saltwater marsh and upland forest to help stabilize shoreline. Project includes berm which reduces flood risk from surge events for the upland Broad Channel community.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms
Estimated Start
2014-03-19T00:00:00.000
Estimated Finish
2019-01-19T00:00:00.000
Estimated Cost
$12,744,000.00
Other Funding Source
DOI
Administrative Technical Capability
Natural Resources Group
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/7132
MA.00292
Hmp Index: MA.00292 • Lead Agency: Department of Parks and Recreation • Action Category: Coastal and Natural Resource Protection
Hmp Index
MA.00292
Mitigation Actions Title
Complete Short-term Beach Nourishment, Dune Construction, and Shoreline Protection on Staten Island (M)
Mitigation Actions Description
Shoreline protection and reinforced dunes have been installed between South Beach and Conference House Park. On Staten Island, the berm projects, along with NPS dune restoration at Miller Field, will create a continuous line of emergency protection from Ocean Ave at South Beach to Fox Lane at Oakwood Beach.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms
Estimated Finish
2014-10-30T00:00:00.000
Estimated Cost
$11,760,000.00
Federal Funding Source
FEMA
City Funding Source
City Capital
Administrative Technical Capability
Resiliency Planning Staff
Financial Capability
406 Mitigation Funding
Web Link
https://www1.nyc.gov/site/sirr/report/report.page
MA.00293
Hmp Index: MA.00293 • Mitigation Actions Title: Increase Growth of Local Plant Material for Restoration Work • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00293
Mitigation Actions Title
Increase Growth of Local Plant Material for Restoration Work
Mitigation Actions Description
Plant beach grass along new sand in the Rockaways and or the existing dunes in Staten Island.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms
Estimated Finish
2015-12-30T00:00:00.000
Estimated Cost
$15,000,000.00
Other Funding Source
Unknown
Administrative Technical Capability
Natural Resources Group
Web Link
https://www1.nyc.gov/site/sirr/report/report.page
MA.00294
Hmp Index: MA.00294 • Mitigation Actions Title: Emergency Protective Measures on Staten Island (M) • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00294
Mitigation Actions Title
Emergency Protective Measures on Staten Island (M)
Mitigation Actions Description
Emergency construction of temporary protective measures at FDR Beach and Boardwalk (R046) from Ocean Avenue South to Ocean Breeze Park, and New Dorp, Oakwood and Cedar Grove Beaches from New Dorp Avenue to Fox Lane, in Great Kills Park (R016) on Staten Island, Borough of Staten Island.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms,Flooding
Estimated Start
2013-04-28T00:00:00.000
Estimated Finish
2013-12-11T00:00:00.000
Estimated Cost
$5,940,000.00
Federal Funding Source
FEMA
City Funding Source
City Capital
MA.00295
Hmp Index: MA.00295 • Mitigation Actions Description: Parks led a conceptual planning process for Staten Island in 2014 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00295
Mitigation Actions Title
Create a Strategic Plan for Public Recreational Land, including the Beachfront Recreation Areas and Open Space
Mitigation Actions Description
Parks led a conceptual planning process for Staten Island in 2014
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms,Flooding
Estimated Cost
$415,000.00
Description Of Social Vulnerability Addressed
Considering priorities of socially vulnerable populations in planning process
Administrative Technical Capability
Resiliency Planning Staff,Long Range Planning and Policy Team
Web Link
https://www.nycgovparks.org/planning-and-building/planning/conceptual-plans/east-shore-shoreline-parks-plan
MA.00296
Hmp Index: MA.00296 • Mitigation Actions Title: Tree planting • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00296
Mitigation Actions Title
Tree planting
Mitigation Actions Description
Partner with stakeholders to help plant one million trees by 2017. Trees reduce temperatures, absorb additional stormwater, and decrease flooding.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Extreme Heat,Flooding
Estimated Start
2017-02-28T00:00:00.000
Estimated Finish
2017-05-31T00:00:00.000
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/8685
Notes
The Millionth tree was planted in 2015 - a recognition event was head in December 2015; Mayor DeBlasio pledged another 100,000 trees.
MA.00297
Hmp Index: MA.00297 • Mitigation Actions Title: Reforestation • Mitigation Actions Description: Plant 470,000 more trees in natural areas.
Hmp Index
MA.00297
Mitigation Actions Title
Reforestation
Mitigation Actions Description
Plant 470,000 more trees in natural areas.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,High Winds
Estimated Start
2017-07-31T00:00:00.000
Estimated Finish
2019-09-30T00:00:00.000
Estimated Cost
$924,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/8868
MA.00298
Hmp Index: MA.00298 • Mitigation Actions Title: Tree pruning • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00298
Mitigation Actions Title
Tree pruning
Mitigation Actions Description
Implement a 7-year program to prune street trees. This program is designed to reduce the impact of Severe Weather including tornadoes, windstorms, and coastal storms.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,High Winds
Estimated Cost
$49,000,000.00
City Funding Source
City Expense
Administrative Technical Capability
Central Forestry Division: Tree Pruning Program
Financial Capability
NYC Capital Budget
Web Link
https://www.nycgovparks.org/services/forestry/tree-pruning
MA.00299
Hmp Index: MA.00299 • Mitigation Actions Title: Queens PLANYC Street Tree Planting FY23 - Community Boards 6, 9 & 10 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00299
Mitigation Actions Title
Queens PLANYC Street Tree Planting FY23 - Community Boards 6, 9 & 10
Mitigation Actions Description
This project will plant new and replacement trees in Community Boards 6, 9 & 10 in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Flooding,Poor Air Quality
Estimated Start
2022-08-01T00:00:00.000
Estimated Finish
2025-02-28T00:00:00.000
Estimated Cost
$2,000,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials,406 Mitigation Funding
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/10419
MA.00300
Hmp Index: MA.00300 • Mitigation Actions Title: Queens Street Tree Planting FY23 - Community Board 7 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00300
Mitigation Actions Title
Queens Street Tree Planting FY23 - Community Board 7
Mitigation Actions Description
This project will plant new and replacement trees in Community Board 7 in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2022-08-01T00:00:00.000
Estimated Finish
2024-12-31T00:00:00.000
Estimated Cost
$900,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
MA.00301
Hmp Index: MA.00301 • Mitigation Actions Title: Queens Street Tree Planting FY23 - Community Boards 1-5 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00301
Mitigation Actions Title
Queens Street Tree Planting FY23 - Community Boards 1-5
Mitigation Actions Description
This project will plant new and replacement trees in Community Boards 1-5 in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2022-08-01T00:00:00.000
Estimated Finish
2025-02-28T00:00:00.000
Estimated Cost
$7,000,000.00
City Funding Source
Mayoral
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials,Public - Private Partnerships (P3s)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/10418
MA.00302
Hmp Index: MA.00302 • Mitigation Actions Title: Queens Park Tree Planting FY22 • Mitigation Actions Description: This project will plant new and replacement park trees in Queens.
Hmp Index
MA.00302
Mitigation Actions Title
Queens Park Tree Planting FY22
Mitigation Actions Description
This project will plant new and replacement park trees in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2021-09-01T00:00:00.000
Estimated Finish
2024-11-30T00:00:00.000
Estimated Cost
$2,858,000.00
City Funding Source
Borough President,Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
MA.00303
Hmp Index: MA.00303 • Mitigation Actions Title: Queens Street Tree Planting FY21 - Community Boards 8, 11-13 • Mitigation Actions Description: This project will plant new trees in Community Boards 8 and 11-13 in Queens.
Hmp Index
MA.00303
Mitigation Actions Title
Queens Street Tree Planting FY21 - Community Boards 8, 11-13
Mitigation Actions Description
This project will plant new trees in Community Boards 8 and 11-13 in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2019-06-01T00:00:00.000
Estimated Finish
2024-10-31T00:00:00.000
Estimated Cost
$17,899,000.00
City Funding Source
Mayoral,City Capital
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
NYC Capital Budget,Public - Private Partnerships (P3s)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9491
MA.00304
Hmp Index: MA.00304 • Mitigation Actions Title: Queens Street Tree Planting FY22 - Community Boards 9-10, 14 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00304
Mitigation Actions Title
Queens Street Tree Planting FY22 - Community Boards 9-10, 14
Mitigation Actions Description
This project will plant new and replacement trees in Community Boards 9, 10, and 14 in Queens.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2021-09-01T00:00:00.000
Estimated Finish
2024-04-30T00:00:00.000
Estimated Cost
$2,531,000.00
City Funding Source
Mayoral,Borough President
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
NYC Capital Budget,Public - Private Partnerships (P3s)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/10185
MA.00305
Hmp Index: MA.00305 • Mitigation Actions Title: Queens Medians Planting and Reconstruction • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00305
Mitigation Actions Title
Queens Medians Planting and Reconstruction
Mitigation Actions Description
This project will reconstruct and replant Bell Malls, Merrick Boulevard Mall and Elmjack Mall.
Lead Agency
Department of Parks and Recreation
Support Agency
Department of Transportation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2015-09-01T00:00:00.000
Estimated Finish
2024-01-30T00:00:00.000
Estimated Cost
$2,000,000.00
City Funding Source
Mayoral,Borough President,City Capital
Description Of Social Vulnerability Addressed
Implementation occurs in communities with high social vulnerability.
Financial Capability
NYC Capital Budget,Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9954
MA.00306
Hmp Index: MA.00306 • Mitigation Actions Title: Powell's Cove Park Shoreline and Upland Area Restoration • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00306
Mitigation Actions Title
Powell's Cove Park Shoreline and Upland Area Restoration
Mitigation Actions Description
This project will restore shoreline and upland area to provide habitat and public access at Powell's Cove Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding,Coastal Erosion
Estimated Start
2022-11-01T00:00:00.000
Estimated Finish
2027-11-30T00:00:00.000
Estimated Cost
$3,000,000.00
City Funding Source
Mayoral,Borough President,City Capital
Administrative Technical Capability
Natural Resources Group
Financial Capability
NYC Capital Budget,Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9779
MA.00307
Hmp Index: MA.00307 • Mitigation Actions Title: Manhattan Lower East Side Street Tree Planting and Community Greening FY22 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00307
Mitigation Actions Title
Manhattan Lower East Side Street Tree Planting and Community Greening FY22
Mitigation Actions Description
This project will plant new and replacement trees on the Lower East Side of Manhattan.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding,Extreme Heat,Poor Air Quality
Estimated Start
2021-09-01T00:00:00.000
Estimated Finish
2024-08-30T00:00:00.000
Estimated Cost
$300,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Implementation occurs in communities with high social vulnerability.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
MA.00308
Hmp Index: MA.00308 • Mitigation Actions Title: Manhattan Park Tree Planting FY22 • Mitigation Actions Description: This project will plant new and replacement park trees in Manhattan
Hmp Index
MA.00308
Mitigation Actions Title
Manhattan Park Tree Planting FY22
Mitigation Actions Description
This project will plant new and replacement park trees in Manhattan
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2021-01-01T00:00:00.000
Estimated Finish
2025-01-30T00:00:00.000
Estimated Cost
$993,000.00
City Funding Source
Mayoral
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
NYC Capital Budget,Funding from Elected Officials,Public - Private Partnerships (P3s)
MA.00309
Hmp Index: MA.00309 • Mitigation Actions Title: Manhattan Street Tree Planting FY21 - Community Boards 1, 2, 4, 5, 7-12 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00309
Mitigation Actions Title
Manhattan Street Tree Planting FY21 - Community Boards 1, 2, 4, 5, 7-12
Mitigation Actions Description
This project will plant new trees in Community Boards 1, 2, 4, 5, and 7-12 in Manhattan.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2019-06-01T00:00:00.000
Estimated Finish
2025-06-30T00:00:00.000
Estimated Cost
$13,565,000.00
City Funding Source
Mayoral,City Capital
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
NYC Capital Budget,Funding from Elected Officials,Public - Private Partnerships (P3s)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9490
MA.00310
Hmp Index: MA.00310 • Mitigation Actions Title: Manhattan Street Tree Planting FY21 - Community Boards 3, 6 • Mitigation Actions Description: This project will plant new trees in Community Boards 3 and 6 in Manhattan.
Hmp Index
MA.00310
Mitigation Actions Title
Manhattan Street Tree Planting FY21 - Community Boards 3, 6
Mitigation Actions Description
This project will plant new trees in Community Boards 3 and 6 in Manhattan.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2019-06-01T00:00:00.000
Estimated Finish
2024-11-30T00:00:00.000
Estimated Cost
$22,784,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9507
MA.00311
Hmp Index: MA.00311 • Mitigation Actions Title: Manhattan Street Tree Planting FY22 - Council District 5 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00311
Mitigation Actions Title
Manhattan Street Tree Planting FY22 - Council District 5
Mitigation Actions Description
This project will plant new and replacement trees in Council District 5 in Manhattan.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2021-09-01T00:00:00.000
Estimated Finish
2024-08-30T00:00:00.000
Estimated Cost
$500,000.00
City Funding Source
City Capital
Private Funding Source
Private
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
NYC Capital Budget,Public - Private Partnerships (P3s)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/10199
MA.00312
Hmp Index: MA.00312 • Mitigation Actions Title: Ridgewood Reservoir Invasive Species Removal • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00312
Mitigation Actions Title
Ridgewood Reservoir Invasive Species Removal
Mitigation Actions Description
This project will remove invasive species and plant new and replacement trees at Ridgewood Reservoir in Highland Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2018-03-01T00:00:00.000
Estimated Finish
2025-10-31T00:00:00.000
Estimated Cost
$3,250,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Highland Park is surrounded by census tracts with high SVI.
Administrative Technical Capability
Natural Resources Group
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9110
MA.00313
Hmp Index: MA.00313 • Mitigation Actions Title: Idlewild Park Reforestation FY21 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00313
Mitigation Actions Title
Idlewild Park Reforestation FY21
Mitigation Actions Description
This project will remove invasive species and plant new and replacement trees in Idlewild Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2020-09-01T00:00:00.000
Estimated Finish
2025-07-31T00:00:00.000
Estimated Cost
$500,000.00
Description Of Social Vulnerability Addressed
Idlewild Park is surrounded by census tracts with high SVI.
Administrative Technical Capability
Borough Forestry Managers
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9789
MA.00314
Hmp Index: MA.00314 • Mitigation Actions Title: Manhattan Reforestation FY20 • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00314
Mitigation Actions Title
Manhattan Reforestation FY20
Mitigation Actions Description
This project will remove invasive species and plant new and replacement trees in Manhattan.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Extreme Heat,Poor Air Quality,Flooding
Estimated Start
2019-05-01T00:00:00.000
Estimated Finish
2026-09-30T00:00:00.000
Estimated Cost
$900,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Heat vulnerability index (which incorporates social vulnerability index) used as a prioritization metric for planting.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9467
MA.00315
Hmp Index: MA.00315 • Mitigation Actions Title: Bridge Park Highbridge Greenway Promenade Construction • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00315
Mitigation Actions Title
Bridge Park Highbridge Greenway Promenade Construction
Mitigation Actions Description
This project will construct a multi-modal pathway with lighting, a passive recreation area, green infrastructure, and shoreline restoration at Bridge Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding,Coastal Erosion
Estimated Start
2019-06-01T00:00:00.000
Estimated Finish
2025-12-31T00:00:00.000
Estimated Cost
$7,500,000.00
State Funding Source
Other State
City Funding Source
Mayoral,Borough President,City Capital
Description Of Social Vulnerability Addressed
Occurring alongside census tracts with high SVI.
Administrative Technical Capability
Resiliency Planning Staff
Financial Capability
NYC Capital Budget,Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/6829
MA.00316
Hmp Index: MA.00316 • Mitigation Actions Title: Crotona Park Indian Lake Shoreline Restoration • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00316
Mitigation Actions Title
Crotona Park Indian Lake Shoreline Restoration
Mitigation Actions Description
This project will remove invasive species and plant new and replacement trees to restore the shoreline of Indian Lake in Crotona Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2019-08-01T00:00:00.000
Estimated Finish
2025-08-30T00:00:00.000
Estimated Cost
$575,000.00
City Funding Source
Borough President,Mayoral
Description Of Social Vulnerability Addressed
Occurring alongside census tracts with high SVI.
Administrative Technical Capability
Natural Resources Group,Borough Offices
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9604
MA.00317
Hmp Index: MA.00317 • Mitigation Actions Title: Crotona Park Tree Planting • Mitigation Actions Description: This project will plant trees in Crotona Park.
Hmp Index
MA.00317
Mitigation Actions Title
Crotona Park Tree Planting
Mitigation Actions Description
This project will plant trees in Crotona Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2021-07-01T00:00:00.000
Estimated Finish
2023-12-31T00:00:00.000
Estimated Cost
$750,000.00
City Funding Source
Mayoral
Description Of Social Vulnerability Addressed
Occurring alongside census tracts with high SVI.
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/10232
MA.00318
Hmp Index: MA.00318 • Mitigation Actions Title: Pelham Bay Park Forest Tree Replacement • Lead Agency: Department of Parks and Recreation
Hmp Index
MA.00318
Mitigation Actions Title
Pelham Bay Park Forest Tree Replacement
Mitigation Actions Description
This project will plant replacement trees and restore native species habitat within forested natural areas in Pelham Bay Park.
Lead Agency
Department of Parks and Recreation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Poor Air Quality,Extreme Heat,Flooding
Estimated Start
2021-02-01T00:00:00.000
Estimated Finish
2025-01-30T00:00:00.000
Estimated Cost
$4,000,000.00
City Funding Source
Mayoral
Administrative Technical Capability
Borough Forestry Managers
Financial Capability
Funding from Elected Officials,Pre-Disaster Mitigation (PDM)
Web Link
https://www.nycgovparks.org/planning-and-building/capital-project-tracker/project/9987