Hazard Mitigation Plan - Mitigation Actions Database

New York City’s comprehensive effort to reduce or eliminate potential losses from the hazards described in the Hazard Specific section of the website. The map includes existing and completed mitigation actions that will minimize the effects of a hazard event on New York City’s population, economy, property, building stock, and infrastructure. It is the result of a coordinated effort by 46 New York City agencies and partners to develop and implement a broad range of inventive and effective ways to mitigate hazards.

NOTE: This table can be joined to the mapped projects using the HMP Index field.
For the Hazard Mitigation Plan map, please follow this link: https://data.cityofnewyork.us/d/n6jh-qsrw

Spatial data for projects that were mapped is available here:
Points: https://data.cityofnewyork.us/City-Government/New-York-City-Emergency-Management-Points-/t7k8-wj6b
Lines: https://data.cityofnewyork.us/City-Government/Hazard-Mitigation-Plan-Mitigation-Actions-Database/hqhh-iv7p
Polygons: https://data.cityofnewyork.us/City-Government/Hazard-Mitigation-Plan-Mitigation-Actions-Database/cj2p-e3ej

City Government NYC Emergency Management (NYCEM) Dataset veqt-eu3t 28 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
MA.00423
Hmp Index: MA.00423 • Mitigation Actions Title: Hardening of EDC Emergency Operations Center • Lead Agency: Economic Development Corporation
Hmp Index
MA.00423
Mitigation Actions Title
Hardening of EDC Emergency Operations Center
Mitigation Actions Description
Raise the emergency generator at the Brooklyn Emergency Operations Center, and upgrade emergency backup systems related to MIS equipment at Brooklyn Emergency Operations Center and Manhattan Asset Management Emergency Operations Center.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Cost
2045-02-07T00:00:00.000
City Funding Source
City Expense
MA.00424
Hmp Index: MA.00424 • Mitigation Actions Title: Wetlands restoration • Lead Agency: Economic Development Corporation
Hmp Index
MA.00424
Mitigation Actions Title
Wetlands restoration
Mitigation Actions Description
Include wetlands restoration as part of waterfront development projects to comply with aesthetic permitting or stormwater management requirements.
Lead Agency
Economic Development Corporation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
State Funding Source
Other State
City Funding Source
City Capital
MA.00425
Hmp Index: MA.00425 • Mitigation Actions Title: Flushing Airport wetlands restoration • Mitigation Actions Description: Implement Flushing Airport Wetlands Mitigation Project in College Point, Queens.
Hmp Index
MA.00425
Mitigation Actions Title
Flushing Airport wetlands restoration
Mitigation Actions Description
Implement Flushing Airport Wetlands Mitigation Project in College Point, Queens.
Lead Agency
Economic Development Corporation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2018-11-30T00:00:00.000
Estimated Finish
2024-11-30T00:00:00.000
Estimated Cost
$9,000,000.00
State Funding Source
Other State
City Funding Source
City Capital
Description Of Critical Facility
The wetland mitigation project goes hand-in-hand with a roadway construction providing critical infrastructure for further development in College Point, Queens.
Planning Regulation Capability
NYC Waterfront Revitization Plan
MA.00426
Hmp Index: MA.00426 • Mitigation Actions Title: Raised Shorelines Citywide • Lead Agency: Economic Development Corporation
Hmp Index
MA.00426
Mitigation Actions Title
Raised Shorelines Citywide
Mitigation Actions Description
Raise bulkheads in low-lying neighborhoods across the city to minimize inland tidal flooding from 2050 sea-level rise.
Lead Agency
Economic Development Corporation
Support Agency
Mayor's Office of Long Term Planning and Sustainability (OLTPS)
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2017-07-31T00:00:00.000
Estimated Finish
2026-12-31T00:00:00.000
Estimated Cost
$69,856,000.00
Federal Funding Source
CDBG
City Funding Source
City Capital
Administrative Technical Capability
HUD Community Development Block Grant - Disaster Recovery (CDBG-DR)
Web Link
https://edc.nyc/project/raise-shorelines-old-howard-beach-mott-basin
MA.00427
Hmp Index: MA.00427 • Mitigation Actions Title: Stapleton waterfront flood mitigation • Lead Agency: Economic Development Corporation
Hmp Index
MA.00427
Mitigation Actions Title
Stapleton waterfront flood mitigation
Mitigation Actions Description
Construct a new tidal wetlands area at the Stapleton waterfront, between Canal and Water Streets, and a pilot stormwater management system in an adjacent public open space to capture stormwater before it reaches the bay.
Lead Agency
Economic Development Corporation
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Flooding
Estimated Start
2016-05-31T00:00:00.000
Estimated Finish
2018-07-31T00:00:00.000
Estimated Cost
$16,000,000.00
Federal Funding Source
FEMA-HMGP
Notes
Project is completed. A portion of the wetlands were modified to be a mud flat due to erosion from tidal action.
MA.00428
Hmp Index: MA.00428 • Mitigation Actions Title: Brooklyn Army Terminal flood resiliency project • Lead Agency: Economic Development Corporation
Hmp Index
MA.00428
Mitigation Actions Title
Brooklyn Army Terminal flood resiliency project
Mitigation Actions Description
The project includes dry floodproofing the basement of Building A and wet floodproofing the basement level of the Annex Building.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding,Coastal Storms
Estimated Start
2017-05-31T00:00:00.000
Estimated Finish
2026-04-01T00:00:00.000
Estimated Cost
$15,853,000.00
Federal Funding Source
FEMA-428
City Funding Source
City Capital
Description Of Critical Facility
The Brooklyn Army Terminal is a City of New York owned and NYCEDC operated facility that provides light manufacturing and office space for businesses in South Brooklyn. The proposed work is an important aspect of
protecting the City’s emergency response infrastructure. This installation will reduce the risk of future damage to BAT Building A and the Annex Building.
Planning Regulation Capability
Hazard Mitigation Plan,Flood Resiliency Guidelines
Administrative Technical Capability
FEMA 428 Program (Group 3)
Notes
Project was awarded to Dewberry in June 2017. Construction is projecting to begin Spring 2024.
MA.00429
Hmp Index: MA.00429 • Mitigation Actions Title: Hunts Point Resiliency Study • Lead Agency: Economic Development Corporation
Hmp Index
MA.00429
Mitigation Actions Title
Hunts Point Resiliency Study
Mitigation Actions Description
Hunts Point Resiliency Study: Project to assess feasibility and develop conceptual design for pilot resiliency project for Food Distribution Center and Hunts Point neighborhood.
Lead Agency
Economic Development Corporation
Action Category
Prevention and Policy
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2016-06-01T00:00:00.000
Estimated Finish
2022-10-31T00:00:00.000
Estimated Cost
$71,000,000.00
Federal Funding Source
CDBG-Rebuild By Design
City Funding Source
City Capital
Description Of Critical Facility
Protection of the Food Distribution Center
Web Link
huntspointresiliency.nyc
MA.00430
Hmp Index: MA.00430 • Mitigation Actions Title: Hunters Point South • Lead Agency: Economic Development Corporation
Hmp Index
MA.00430
Mitigation Actions Title
Hunters Point South
Mitigation Actions Description
The entire 11 acre Hunters Point South Park is designed with resilient materials that can be completely inundated with water and drained during a large storm event. The phase II park features over an acre of tidal wetlands that protects the housing parcels behind them.
Lead Agency
Economic Development Corporation
Action Category
Coastal and Natural Resource Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms,Flooding
Estimated Start
2018-12-30T00:00:00.000
State Funding Source
City Capital
Web Link
https://www.nycedc.com/press-release/city-opens-sprawling-55-acre-waterfront-park-hunters-point-south-long-island-city
MA.00431
Hmp Index: MA.00431 • Mitigation Actions Title: MARSHES Mitigation Banking Pilot (Saw Mill Creek) • Mitigation Actions Description: Constructing a wetland that will serve as NYC's first wetland mitigation bank.
Hmp Index
MA.00431
Mitigation Actions Title
MARSHES Mitigation Banking Pilot (Saw Mill Creek)
Mitigation Actions Description
Constructing a wetland that will serve as NYC's first wetland mitigation bank.
Lead Agency
Economic Development Corporation
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms,Flooding
Estimated Start
2025-10-31T00:00:00.000
Federal Funding Source
PANYNJ
State Funding Source
City Expense
Other Funding Source
1
Description Of Social Vulnerability Addressed
0
Description Of Critical Facility
City Environmental Quality Review (CEQR)
Administrative Technical Capability
Capital Program
Web Link
https://www.nycedc.com/project/marshes-initiative
MA.00432
Hmp Index: MA.00432 • Mitigation Actions Title: Coney Island Creek Raised Shoreline • Lead Agency: Economic Development Corporation
Hmp Index
MA.00432
Mitigation Actions Title
Coney Island Creek Raised Shoreline
Mitigation Actions Description
Work includes bulkhead repair and the creation of a living shoreline along Coney Island Creek.
Lead Agency
Economic Development Corporation
Support Agency
Mayor's Office of Long Term Planning and Sustainability (OLTPS)
Action Category
Coastal and Natural Resource Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Erosion,Coastal Storms,Flooding
Estimated Start
2018-10-31T00:00:00.000
Estimated Cost
$73,000,000.00
Federal Funding Source
CDBG-Rebuild By Design,FEMA-BRIC
City Funding Source
City Capital
MA.00433
Hmp Index: MA.00433 • Mitigation Actions Title: Hunts Point Food Security Mitigation Project • Lead Agency: Economic Development Corporation
Hmp Index
MA.00433
Mitigation Actions Title
Hunts Point Food Security Mitigation Project
Mitigation Actions Description
Implement cost-effective building hardening solutions to protect two of the most at-risk facilities and the critical food they supply: 355 Food Center Drive (the Meat Market), and 600 Food Center Drive. These interventions--including the use of deployable floodgate technology that will be erected in advance of a storm event, submersible glass to floodproof buildings, and a concrete wall to reinforce building walls--will be designed to the 90th percentile for sea-level rise in the 2050s, ensuring that these protections anticipate future conditions.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2023-12-04T00:00:00.000
Estimated Finish
2027-01-01T00:00:00.000
Estimated Cost
$19,514,452.72
Federal Funding Source
FEMA-BRIC
Description Of Critical Facility
Protecting vulnerable facilities within the Food Distribution Center
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
Flood Mitigation Assistance (FMA),Water and sewer funds
MA.00434
Hmp Index: MA.00434 • Mitigation Actions Title: Hunts Point Meat Market & 600 Food Center Drive • Lead Agency: Economic Development Corporation
Hmp Index
MA.00434
Mitigation Actions Title
Hunts Point Meat Market & 600 Food Center Drive
Mitigation Actions Description
Implement cost-effective building hardening solutions to protect two of the most at-risk facilities and the critical food they supply: 355 Food Center Drive --the Meat Market, and 600 Food Center Drive. These interventions will be designed to the 90th percentile for sea-level rise in the 2050s, ensuring that these protections anticipate future conditions.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Cost
$19,493,452.00
Federal Funding Source
FEMA-BRIC
Description Of Critical Facility
Protecting vulnerable facilities in the Food Distribution Center
Notes
4 years duration
MA.00435
Hmp Index: MA.00435 • Mitigation Actions Title: Lower Manhattan Resilient Stormwater Pump Station • Lead Agency: Economic Development Corporation
Hmp Index
MA.00435
Mitigation Actions Title
Lower Manhattan Resilient Stormwater Pump Station
Mitigation Actions Description
The City of New York, through its Department of Small Business Services (NYCSBS) operating through the New York City Economic Development Corporation (NYCEDC), is aiming to advance the preliminary design of a new wet-weather pump station and associated drainage improvements in Lower Manhattan. The project would mitigate the impact of flood hazards in one of NYC’s central business districts and critical transportation hubs, help to prevent devastating economic losses such as those that the area has experienced in recent years, and maintain safe, uninterrupted transportation service for millions of people. NYCEDC selected this project as a priority for funding because the pump station is critical to prevent severe economic losses, infrastructural damage, and safety risks from wet weather conditions. It will also support the success of the City’s planned larger coastal protection improvements. Based on extensive studies conducted by NYCEDC in Lower Manhattan during the Financial District and Seaport Master Plan it was determined that the recurrent tidal flooding and coastal storm surge will block existing outfalls that typically release combined stormwater and wastewater during heavy rain events; if no action is taken, this will result in flooding behind the larger flood defense system in development. To address these issues, a new wet-weather pump station and associated drainage improvements are needed. Unlike regular pumps that manage normal water flow, a wet-weather pump operates during extreme weather to handle the extra volume. The new pump station and drainage infrastructure must adapt to (1) frequent and severe rain events, (2) the impacts of storm surge on the combined sewer system, and (3) the isolation of the drainage system by neighboring coastal protection projects. To meet these criteria, the pump station will need a pumping capacity of 250-350M gallons per day. This pump station would be the first of its kind in NYC. The pump station would only operate during emergency flood conditions. The goals of the proposed project are:

(1) Advance design development of stormwater management infrastructure, including a pump station and associated drainage improvements, to preliminary design to be ready to begin environmental review and permitting;

(2) Conduct stakeholder engagement and partnership building to inform a successful and comprehensive design; and

(3) Complete a FEMA-compliant benefit-cost analysis (BCA) and a subapplication for a future HMA grant to complete design, permitting, and construction.

This scope of work will result in the preliminary (30%) design of stormwater management infrastructure that can be submitted in a future HMA application cycle to complete the design, permit, and construct the project. Deliverables will include preliminary design of a pump station and associated drainage improvements (including new conveyance sewers, flood-proofing of sewer manholes and tide gates, force-main discharge piping for the pump station, and complementary green infrastructure located at the pump station), a Basis of Design Report, a benefit-cost analysis, and documentation of robust stakeholder engagement. The documentation will be included as attachments/inputs in the project implementation grant application to be submitted in a future grant cycle.
Description Problem
The Financial District and Seaport area in particular is characterized by paved surfaces with little green space to absorb water into the ground. As a result, water directly enters the sewer system, primarily through storm drains along the streets. The area is served by a combined sewer system, meaning that stormwater and wastewater are managed by the same sewers. During medium and larger storms, the excess flows that cannot be conveyed to the Newton Creek Wastewater Resource Recovery Facility are discharged to the East River through existing combined sewer overflow (CSO) pipes by gravity. Higher tides and/or storm surge prevent these gravity discharges and result in the system flooding onto the street or into basements. To respond to the increasing hazards posed by flooding, while transforming the waterfront to better serve all New Yorkers for generations to come, the City released the Financial District and Seaport Master Plan (Master Plan) in December 2021. However, with or without the drainage improvements from nearby resilience projects proposed through the Master Plan, the Financial District and Seaport neighborhoods are still at risk of flooding and need a local solution—a new wet-weather pump station.

Further computer modeling was conducted by EDC to understand the magnitude and location of flooding that may occur absent new drainage infrastructure in the proposed location. The model simulated the five-year and 50-year rainstorms coincident with a 100-year storm surge event by 2100. The modeling revealed that, absent new drainage infrastructure, flooding could be more than five feet deep in some areas and that this will only get worse over time. The modeling also showed that flooding occurs during rainfall-only events, without surge conditions, under anticipated sea level rise conditions. Most of this flooding will come from the combined sewer system in low-lying areas near the shoreline. Without proactive measures, the financial consequences of these extreme weather events will be dire: projections through 2100 indicate flooding could result in up to $20.3B in losses across the Lower Manhattan area and region if flood protection measures are not implemented. This includes $15.1B in direct and indirect economic impacts, alongside expected disruptions to the transportation systems that are critical to the city and region’s economy and workforce mobility.
Lead Agency
Economic Development Corporation
Support Agency
Department of Environmental Protection, Small Business Services
Action Category
Property Protection
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2027-01-01T00:00:00.000
Estimated Finish
2029-09-30T00:00:00.000
Estimated Cost
$6,280,000.00
Federal Funding Source
FEMA-HMGP
Description Of Social Vulnerability Addressed
According to U.S. DOT Areas of Persistent Poverty (AoPP) data, the proposed pump station location is adjacent to six (6) tracts identified as AoPP in Manhattan. The projected drainage area for the pump station encompasses 30 census tracts who are particularly underserved by housing and transportation because they live in multi-unit structures--which may be subject to unhealthy crowding or group quarters conditions--and may not have access to a vehicle. Moreover, according to the FEMA Community Disaster Resilience Zone (CDRZ) viewer tool the proposed project will benefit a nearby CDRZ (tract 3606100150). This tract is located within Lower Manhattan and includes portions of South Street Seaport, FDR Drive, Lower Manhattan Hospital, and various subway lines that serve the Financial District/Seaport Area—which together provide critical access to local and regional transportation connections, essential services, and economic activities.
MA.00436
Hmp Index: MA.00436 • Mitigation Actions Title: Resilient Staten Island Ferry Terminal  • Lead Agency: Economic Development Corporation
Hmp Index
MA.00436
Mitigation Actions Title
Resilient Staten Island Ferry Terminal Â
Mitigation Actions Description
The New York City Economic Development Corporation proposes the planning and design of a new, resilient Staten Island Ferry Terminal (SIFT) in New York City (NYC) to protect the Terminal against destructive flooding hazards and to maintain the reliability of Staten Island Ferry service during and after extreme weather events. The project targets two levels of flood protection: (1) maintaining ferry service despite the impacts of increased ocean levels and expected higher tides (“sunny day” conditions) and (2) protecting the facility from increasingly frequent and severe coastal storms, including the significant impact of waves and wave action. The project will conduct surveying, modeling, and economic analyses to reach a preliminary (30%) stage of design for a Staten Island Ferry Terminal that is comprehensively safeguarded against multiple flooding hazards to preserve operations, avoid costly disruptions and structural damage, and maintain ferry safety, accessibility, and service for millions of annual passengers.  

This project scoping activity has three key goals:
1) Advance the design development of a new, resilient SIFT to begin environmental review and permitting. This would focus on three main systems: (1) the flood protection system (e.g., passive elevation features, floodwalls, gates), (2) marine structures and systems (e.g., dolphins, fenders, piers, ramps, and related requirements), (3) the building/facility system (e.g., building envelop, structural, foundations, interior spaces, passenger services). This would include identification of major design elements across architectural, civil, structural, mechanical, and other disciplines. Efforts include creating plans, sections, and specifications, assessing existing conditions, integrating flood protection, and analyzing space requirements for marine operations and passenger movement. The design will emphasize economic resilience by aiming to minimize ferry service disruptions by evaluating constructability, staging, and temporary relocation of operations during construction.

2) Conduct stakeholder engagement and partnership building to inform a successful and comprehensive design; and

3) Complete a FEMA-compliant economic impact analysis and benefit-cost analysis (BCA) for a preferred design.

This scope of work will result in preliminary (30%) design of the flood protection and marine structures and systems such that a new, resilient SIFT that can be submitted in a future HMA application cycle to complete the design and implement the project. Deliverables will include schematic design of the ferry terminal, documentation of robust stakeholder engagement, an economic impact analysis, a benefit-costs analysis (BCA), and a subapplication for a future HMA funding opportunity. The documentation will be included as attachments/inputs in the project implementation grant application to be submitted in a future grant cycle, to position the City to secure additional funding for final design, permitting, and construction.
Description Problem
The current Whitehall Ferry Terminal, which the new SIFT will replace, faces growing challenges from recurring coastal flooding and severe weather, which threaten its long-term functionality and economic viability. If no action is taken, by the 2050s daily tides will reduce the clearance between the top ferry deck and roof of the Terminal. This could require steeper boarding ramps which can be challenging for all users, along with compromising compliance with accessibility regulations such as American Disabilities Act (ADA) and NYC Local Law 68. By the 2080s, the lower level will be submerged daily, which will not only block lower-level boarding but impede operations of the whole facility entirely, leading to costly infrastructure damages and disrupting ferry services relied on by thousands of daily commuters to access their jobs. In addition to tidal flooding, the Terminal is at risk from more frequent and severe storms, like hurricanes and nor’easters. Without proactive measures, the financial consequences of these extreme weather events on the Terminal and surrounding community would be dire: projections through 2100 indicate flooding could result in up to $20.3B in losses across the Lower Manhattan area and region if flood protection measures are not implemented. This includes $15.1B in direct and indirect economic impacts, alongside expected disruptions to the transportation systems that are critical to the city and region’s economy and workforce mobility.

In 2021, NYC released the Financial District and Seaport Climate Resilience Master Plan (Master Plan), which outlines long-term strategies to protect Lower Manhattan from severe coastal storms and rainfall through integrated coastal resilience projects. In identifying an areawide flood protection system to prevent flooding of the entire neighborhood, the Master Plan also identified the need for the current Whitehall Ferry Terminal to be reconstructed and made resilient to maintain Ferry service. The challenges of reconstructing this critical ferry terminal are compounded by the fact that it sits on top of and astride multiple subway tunnels. Additionally, the areawide protection for the stretch of shoreline along the Financial District and Seaport neighborhoods will need to be integrated into the Ferry Terminal. Therefore, it is proposed that the terminal be rebuilt as the new “Staten Island Ferry Terminal” to mitigate flooding hazards, maintain continuity of Staten Island Ferry service, and integrate with the larger planned flood defense system. The City will also explore opportunities to seamlessly integrate the flood protection and resilience components while improving passenger experience as well as accommodating projected future passenger increases.
Lead Agency
Economic Development Corporation
Support Agency
New York City Department of Transportation, Small Business Services
Action Category
Property Protection
Action Status
Proposed or Not Started
Action Status Date
2025-02-20T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2027-01-01T00:00:00.000
Estimated Finish
2029-06-30T00:00:00.000
Estimated Cost
$4,710,000.00
Federal Funding Source
FEMA-HMGP
Description Of Critical Facility
According to U.S. DOT Areas of Persistent Poverty (AoPP) data, Manhattan and SI poverty rates surpass the national average (11.1%), with Manhattan boroughs reporting at 16.5% and SI at 13.1% of people living in poverty. The median household income of SI is approximately $95,543, categorizing the average SI resident as low-income with a 68% AMI, according to 2023 Census data and the U.S Department of Housing and Urban Development (HUD). The proposed Ferry Terminal location is adjacent to six (6) tracts identified as AoPP in Manhattan and—since over half of the Ferry’s resident riders are Staten Island residents—also offers a critical service to the twenty-nine (29) AoPP tracts in Staten Island. These residents rely on the Ferry, a free service, as a cost-effective alternative to using express buses or driving to reach Manhattan. The Ferry also offers a more time-efficient transportation connection to Lower Manhattan, where traffic congestion is among the worst in the nation, costing residents hundreds of hours annually and delaying access to jobs, schools, local businesses, and essential services.
MA.00437
Hmp Index: MA.00437 • Mitigation Actions Title: Seaport Base Flood Infrastructure Study • Lead Agency: Economic Development Corporation
Hmp Index
MA.00437
Mitigation Actions Title
Seaport Base Flood Infrastructure Study
Mitigation Actions Description
The project will advance and refine the design of the project’s base flood defense infrastructure. Deliverables will include a schematic design report, which will be publicly released, and a public open house to gather feedback on the design.
Lead Agency
Economic Development Corporation
Action Category
Coastal and Natural Resource Protection
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2024-02-29T00:00:00.000
Estimated Finish
2027-02-28T00:00:00.000
Estimated Cost
$3,500,000.00
Federal Funding Source
FEMA
Other Funding Source
Other
Web Link
https://fidiseaportclimate.nyc/
MA.00438
Hmp Index: MA.00438 • Mitigation Actions Title: Green roofs • Lead Agency: Economic Development Corporation
Hmp Index
MA.00438
Mitigation Actions Title
Green roofs
Mitigation Actions Description
Install green roofs on facilities where appropriate to reduce the volume of stormwater runoff by absorbing or storing water and help reduce the urban heat island effect.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Extreme Heat,Flooding
Private Funding Source
Unknown
MA.00440
Hmp Index: MA.00440 • Mitigation Actions Title: Expansion of ferry landings available for regular and emergency use. • Lead Agency: Economic Development Corporation
Hmp Index
MA.00440
Mitigation Actions Title
Expansion of ferry landings available for regular and emergency use.
Mitigation Actions Description
Design and procure two new ferry landing barges that are outfitted with the required equipment for providing basic ferry service, including self-contained generators. These barges will be stored in a secure and protected location. When the need arises, they will be deployed within 24 to 48 hours as temporary landings, allowing for the rapid establishment of interim service. Deploy four new permanent ferry landings at strategic locations selected based on the results of the ongoing Citywide Ferry Study. The landings will be designed to be mobile so that, in an extreme situation, they can be temporarily relocated to provide alternative transit services where needed.
Lead Agency
Economic Development Corporation
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Cost
$15,000,000.00
Federal Funding Source
FTA
MA.00441
Hmp Index: MA.00441 • Mitigation Actions Title: Infrastructure upgrade Ferry Landings • Lead Agency: Economic Development Corporation
Hmp Index
MA.00441
Mitigation Actions Title
Infrastructure upgrade Ferry Landings
Mitigation Actions Description
Provide technical assistance to inform the design and installation of passenger ferry landings. EDC has experience with regard to the mooring, anchoring, and stabilization mechanisms available for ferry landings that are able to withstand the effects of various natural hazard events.
Lead Agency
Economic Development Corporation
Action Category
Prevention and Policy
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Non-Natural
State Funding Source
City Capital
Private Funding Source
Other
Notes
$55M City wide ferry service is under construction adding more than 20 ferry landings and expected to be fully operational in 2018
MA.00442
Hmp Index: MA.00442 • Mitigation Actions Title: Infrastructure upgrade Arthur Kill • Lead Agency: Economic Development Corporation
Hmp Index
MA.00442
Mitigation Actions Title
Infrastructure upgrade Arthur Kill
Mitigation Actions Description
Upgrade Arthur Kill lift bridge including possible construction of new bulkheads/pier.
Lead Agency
Economic Development Corporation
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Coastal Erosion,Flooding
State Funding Source
City Capital
MA.00443
Hmp Index: MA.00443 • Mitigation Actions Title: Food distribution system • Mitigation Actions Description: Study the system to identify vulnerabilities.
Hmp Index
MA.00443
Mitigation Actions Title
Food distribution system
Mitigation Actions Description
Study the system to identify vulnerabilities.
Lead Agency
Economic Development Corporation
Support Agency
Mayor's Office of Long Term Planning and Sustainability (OLTPS)
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Finish
2015-12-31T00:00:00.000
Estimated Cost
$3,000,000.00
Federal Funding Source
CDBG
Web Link
https://www.nycedc.com/system/files/files/resource/2016_food_supply-resiliency_study_results.pdf
MA.00444
Hmp Index: MA.00444 • Mitigation Actions Title: Industrial property upgrades • Mitigation Actions Description: Implement planned upgrades to vulnerable City-owned industrial properties.
Hmp Index
MA.00444
Mitigation Actions Title
Industrial property upgrades
Mitigation Actions Description
Implement planned upgrades to vulnerable City-owned industrial properties.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Non-Natural
Estimated Cost
$10,000,000.00
Federal Funding Source
FEMA-HMGP
MA.00445
Hmp Index: MA.00445 • Lead Agency: Economic Development Corporation • Action Category: Property Protection
Hmp Index
MA.00445
Mitigation Actions Title
Hardening Staten Island Ferry and private ferry terminals from climate change-related threats
Mitigation Actions Description
Construct physical improvements to the floating infrastructure, loading gangways, pilings, and piers, as well as develop a stock of spare parts to be stored in a secure upland location.
Lead Agency
Economic Development Corporation
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Cost
$15,000,000.00
Federal Funding Source
FTA
MA.00446
Hmp Index: MA.00446 • Mitigation Actions Title: Construction of new ferry landings to support private ferry services • Lead Agency: Economic Development Corporation
Hmp Index
MA.00446
Mitigation Actions Title
Construction of new ferry landings to support private ferry services
Mitigation Actions Description
Expand the network of ferry landings available for both regular and emergency use. Design and procure two new ferry landing barges that are outfitted with the required equipment for providing basic ferry service, including self-contained generators.
Lead Agency
Economic Development Corporation
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Finish
2018-12-31T00:00:00.000
Estimated Cost
$15,000,000.00
Federal Funding Source
FTA
City Funding Source
City Capital
Description Of Social Vulnerability Addressed
This is especially critical in a metropolitan area that consists primarily of islands and peninsulas, and in which the majority of the population lives in coastal communities The use of ferries to provide contingency and surge service in the event of a disruption to the regional transportation network is a component of the City’s emergency planning efforts.
Notes
Work to be performed as part of City wide ferry service and to be complete by 2019
MA.00447
Hmp Index: MA.00447 • Mitigation Actions Title: Mobile ferry ticketing machines • Lead Agency: Economic Development Corporation
Hmp Index
MA.00447
Mitigation Actions Title
Mobile ferry ticketing machines
Mitigation Actions Description
Procure up to 15 mobile ticketing machines to provide a flexible ticketing solution that can be moved to ferry landings experiencing high-volume ridership in post-storm periods to reduce wait times and enable a more efficient flow of passengers to final destinations.
Lead Agency
Economic Development Corporation
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Start
2018-12-31T00:00:00.000
Private Funding Source
Authority Capital
Notes
Work to be performed as part of City wide ferry service and to be complete by 2019
MA.00448
Hmp Index: MA.00448 • Lead Agency: Economic Development Corporation • Action Category: Infrastructure Projects
Hmp Index
MA.00448
Mitigation Actions Title
Use of the Staten Island Ferry's Austen Class vessels for East River Ferry service during weather-related disruptions
Mitigation Actions Description
Supplement East River Ferry capacity during transit service disruptions that cause large numbers of commuters to use ferry services by retrofitting existing ferry landings to accommodate the Austen Class vessels.
Lead Agency
Economic Development Corporation
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Start
2019-11-30T00:00:00.000
State Funding Source
City Capital
Notes
Work to be performed as part of City wide ferry service and to be complete by 2019. Additionally design will support DOT's next generation Staten Island Ferry vessel
MA.00449
Hmp Index: MA.00449 • Mitigation Actions Title: Waterfront fueling facilities • Lead Agency: Economic Development Corporation
Hmp Index
MA.00449
Mitigation Actions Title
Waterfront fueling facilities
Mitigation Actions Description
Retrofit one or two waterfront fueling facilities to accommodate large commercial vessels, including ferry boats and other government vessels.
Lead Agency
Economic Development Corporation
Action Category
Prevention and Policy
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Non-Natural
Private Funding Source
Unknown
MA.00450
Hmp Index: MA.00450 • Mitigation Actions Title: FDNY emergency services • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00450
Mitigation Actions Title
FDNY emergency services
Mitigation Actions Description
Expand FDNY capabilities to respond to natural hazards. In the wake of Hurricane Sandy, the FDNY identified initiatives that would enhance its capabilitiesincluding GPS for apparatus, additional boats for high-water rescue and pumping, and other all-weather vehiclesand ultimately allow the FDNY to act as the City's primary response agency.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms
Estimated Start
2012-12-31T00:00:00.000
Estimated Finish
2015-12-30T00:00:00.000
Estimated Cost
$1,000,000.00
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
The FDNY used DHS funds to purchase high-volume pumping systems, dewatering equipment, high-pumping fireboats, small rapid response craft, swift water rescue boats, zodiac rescue boats, swift water rescue suits and PPE, personal flotation devices, and hig
MA.00451
Hmp Index: MA.00451 • Mitigation Actions Title: EMS Station 43 / Coney Island Shops • Mitigation Actions Description: Restore service to damaged building's electrical, floors, walls, sewage, etc.
Hmp Index
MA.00451
Mitigation Actions Title
EMS Station 43 / Coney Island Shops
Mitigation Actions Description
Restore service to damaged building's electrical, floors, walls, sewage, etc.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms
Estimated Start
2012-10-31T00:00:00.000
Estimated Finish
2013-01-31T00:00:00.000
Estimated Cost
$1,190,000.00
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00452
Hmp Index: MA.00452 • Mitigation Actions Title: EMS fallback sites • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00452
Mitigation Actions Title
EMS fallback sites
Mitigation Actions Description
Identify fallback sites within the EMS facility network for EMS stations (23% of FDNY EMS stations) located in or near flood zones. Sites would be equipped with basic technology and sufficient storage capacity to allow EMS to initiate operations in the event of a catastrophe.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms
Estimated Cost
$2,500,000.00
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00453
Hmp Index: MA.00453 • Mitigation Actions Title: Dewatering pumps at FDNY facilities • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00453
Mitigation Actions Title
Dewatering pumps at FDNY facilities
Mitigation Actions Description
Portable dewatering pumps have been purchased for field units. Auxiliary pumping unit can pump an estimated 3,000 gallons of water per minute.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding
Estimated Start
2013-12-31T00:00:00.000
Estimated Finish
2015-12-30T00:00:00.000
Estimated Cost
$75,000.00
Federal Funding Source
Other Federal
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
Portable dewatering pumps have been purchased with DHS funds. Auxiliary pumping unit can pump an estimated 3,000 gallons of water per minute.
MA.00454
Hmp Index: MA.00454 • Mitigation Actions Title: Voice-over IP (VOIP) architecture • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00454
Mitigation Actions Title
Voice-over IP (VOIP) architecture
Mitigation Actions Description
Explore feasibility of switching to more resilient voice-over IP architecture. VOIP is in service (provided by Verizon)at the backup FDOC in Staten Island
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding,High Winds,Winter Weather,Non-Natural,Earthquakes
Estimated Start
2014-12-31T00:00:00.000
Estimated Finish
2016-12-30T00:00:00.000
Estimated Cost
$1,000,000.00
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
VOIP does not support FDNY firehouse Centrex lines or any centrex lines- VOIP is in service (provided by Verizon)at the backup FDOC in Staten Island
MA.00455
Hmp Index: MA.00455 • Mitigation Actions Title: Fire Department Operations Center (FDOC) cell phone coverage • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00455
Mitigation Actions Title
Fire Department Operations Center (FDOC) cell phone coverage
Mitigation Actions Description
Improve cell phone coverage of FDOC, which FDNY staffs with additional personnel during major events, taxing the already overcrowded and sometimes unavailable cell network.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding,High Winds,Winter Weather,Non-Natural,Earthquakes
Estimated Start
2013-12-31T00:00:00.000
Estimated Finish
2017-12-30T00:00:00.000
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00456
Hmp Index: MA.00456 • Mitigation Actions Title: Cache of vaccinations • Mitigation Actions Description: Ensure a sufficient supply of vaccines to inoculate all first responders.
Hmp Index
MA.00456
Mitigation Actions Title
Cache of vaccinations
Mitigation Actions Description
Ensure a sufficient supply of vaccines to inoculate all first responders.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Disease Outbreak
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
The FDNY Emergency Medical Service maintains a cache of WMD antidote to treat upwards of 100,000 people and responders in the event of a WMD-type attack.
MA.00457
Hmp Index: MA.00457 • Mitigation Actions Title: Urban search and rescue team • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00457
Mitigation Actions Title
Urban search and rescue team
Mitigation Actions Description
Increase the number of trained officers and firefighters in New York Task Force 1 to meet the growing demands of a professional, trained, and proven search and rescue team.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds
Estimated Start
2013-12-31T00:00:00.000
Estimated Finish
2016-12-30T00:00:00.000
Estimated Cost
$500,000.00
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00459
Hmp Index: MA.00459 • Mitigation Actions Title: Power redundancy at FDNY facilities • Mitigation Actions Description: Install backup electrical power generators in all FDNY facilities.
Hmp Index
MA.00459
Mitigation Actions Title
Power redundancy at FDNY facilities
Mitigation Actions Description
Install backup electrical power generators in all FDNY facilities.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Non-Natural
Estimated Start
2001-12-31T00:00:00.000
Estimated Finish
2025-12-30T00:00:00.000
Estimated Cost
$300,000.00
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
70% have back up generators that can power the entire building. (72 hour fuel supply)
MA.00460
Hmp Index: MA.00460 • Mitigation Actions Title: Water supply redundancy • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00460
Mitigation Actions Title
Water supply redundancy
Mitigation Actions Description
Increase water drafting capabilities citywide. Drafting, which entails the suction of water from a body of water to a fire apparatus, can decrease the demand on the water supply system and provide redundant fire suppression water in the event of a drought or earthquake-induced water supply disruption.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Earthquakes,Drought
Estimated Start
2015-12-31T00:00:00.000
Estimated Finish
2018-05-31T00:00:00.000
Estimated Cost
$250,000.00
Other Funding Source
Other
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00461
Hmp Index: MA.00461 • Mitigation Actions Title: Continuity of Operations Plan (COOP) • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00461
Mitigation Actions Title
Continuity of Operations Plan (COOP)
Mitigation Actions Description
Create, distribute, and implement a COOP plan to ensure continuity of all FDNY operations in the event of a disaster.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Disease Outbreak,Drought,Non-Natural
Estimated Start
2007-12-31T00:00:00.000
Estimated Cost
$810,000.00
Other Funding Source
Other
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00462
Hmp Index: MA.00462 • Mitigation Actions Title: Emergency action plans • Mitigation Actions Description: Require non-fire emergency plans for office buildings.
Hmp Index
MA.00462
Mitigation Actions Title
Emergency action plans
Mitigation Actions Description
Require non-fire emergency plans for office buildings.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Extreme Heat,Flooding,High Winds,Winter Weather,Disease Outbreak,Drought,Non-Natural
Estimated Start
2012-12-31T00:00:00.000
Estimated Finish
2019-12-30T00:00:00.000
Estimated Cost
$1,400,000.00
Other Funding Source
Other
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00463
Hmp Index: MA.00463 • Mitigation Actions Title: IT disaster recovery • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00463
Mitigation Actions Title
IT disaster recovery
Mitigation Actions Description
Create, distribute, and implement a recovery plan to ensure continuity of IT operations in the event of a disaster.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Earthquakes,High Winds,Winter Weather,Non-Natural
Estimated Start
2013-12-31T00:00:00.000
Estimated Finish
2016-12-30T00:00:00.000
Estimated Cost
$2,400,000.00
Other Funding Source
Other
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00464
Hmp Index: MA.00464 • Mitigation Actions Title: Backup communications carrier • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00464
Mitigation Actions Title
Backup communications carrier
Mitigation Actions Description
Research the feasibility of using a commercial carrier to back up NYCWiN until NYCWiN can be hardened and made more resilient. FDNY cable network: Upgrade FDNY's cable network, which connects dispatch centers with firehouses to relay 911 calls, to fiber to improve resiliency and reduce outages.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding,High Winds,Non-Natural
Estimated Start
2016-12-31T00:00:00.000
Estimated Finish
2018-12-31T00:00:00.000
Estimated Cost
$160,000,000.00
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00465
Hmp Index: MA.00465 • Mitigation Actions Title: Next-generation satellite phones • Mitigation Actions Description: Purchase "smart" satellite phones and radios for critical staff.
Hmp Index
MA.00465
Mitigation Actions Title
Next-generation satellite phones
Mitigation Actions Description
Purchase "smart" satellite phones and radios for critical staff.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Winter Weather,Non-Natural
Estimated Cost
$125,000.00
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00466
Hmp Index: MA.00466 • Mitigation Actions Title: Spare radios • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00466
Mitigation Actions Title
Spare radios
Mitigation Actions Description
Acquire additional portable radios to facilitate more widespread use of FDNY trunking system during cell carrier outages.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,Non-Natural
Estimated Start
2015-12-31T00:00:00.000
Estimated Finish
2019-12-30T00:00:00.000
Estimated Cost
$1,000,000.00
Federal Funding Source
FEMA-HMGP
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
FDNY Radio shops is in the process of purchasing the Motorola APX 8000 model, they will all be trunked capable.
MA.00467
Hmp Index: MA.00467 • Mitigation Actions Title: Gas vendors • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00467
Mitigation Actions Title
Gas vendors
Mitigation Actions Description
Work with DCAS to ensure they maintain spare fuel supply in the event of shortages. Obtained 2 Fuel trucks.
Lead Agency
Fire Department of the City of New York
Action Category
Emergency Services
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Flooding,Non-Natural,Coastal Storms
Estimated Cost
$750,000.00
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00468
Hmp Index: MA.00468 • Mitigation Actions Title: FDNY facilities survey • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00468
Mitigation Actions Title
FDNY facilities survey
Mitigation Actions Description
Conduct a survey of FDNY facilities and facility components (e.g., roofs, doors, windows) in the revised FEMA flood zones, and schedule upgrades.
Lead Agency
Fire Department of the City of New York
Action Category
Infrastructure Projects
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2012-12-31T00:00:00.000
Estimated Cost
$2,500,000.00
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00469
Hmp Index: MA.00469 • Mitigation Actions Title: Home-work plans • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00469
Mitigation Actions Title
Home-work plans
Mitigation Actions Description
Explore feasibility of telecommuting options for non-emergency personnel who support critical operations during disasters.
Lead Agency
Fire Department of the City of New York
Action Category
Prevention and Policy
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Earthquakes,Flooding,High Winds,Winter Weather,Non-Natural
Estimated Start
2015-12-31T00:00:00.000
Estimated Finish
2019-12-30T00:00:00.000
Estimated Cost
$250,000.00
City Funding Source
City Expense
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
Personnel now have laptops and wifi cards.
MA.00470
Hmp Index: MA.00470 • Mitigation Actions Title: Marine Company 1 Wave Screens • Mitigation Actions Description: Conduct feasibility study of repair/mitigation or replacing the structure
Hmp Index
MA.00470
Mitigation Actions Title
Marine Company 1 Wave Screens
Mitigation Actions Description
Conduct feasibility study of repair/mitigation or replacing the structure
Lead Agency
Fire Department of the City of New York
Action Category
Property Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2019-06-30T00:00:00.000
Estimated Finish
2020-12-30T00:00:00.000
Estimated Cost
$75,705.00
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00472
Hmp Index: MA.00472 • Mitigation Actions Title: Marine 9 - Wave Attenuator • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00472
Mitigation Actions Title
Marine 9 - Wave Attenuator
Mitigation Actions Description
Construct and install three new berthing monopiles with rubber fenders. This provides the most protection for the Fire Fighter II (FF II), Fire House, berthing of the FFII, ramps and decking.
Lead Agency
Fire Department of the City of New York
Action Category
Property Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2014-06-30T00:00:00.000
Estimated Finish
2015-06-29T00:00:00.000
Estimated Cost
$110,382.82
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
FDNY Administrative Internal Priority
MA.00473
Hmp Index: MA.00473 • Mitigation Actions Title: EMS 4 Flood Protection • Mitigation Actions Description: Raise utilities, wet floodproof building, raise generator on platform.
Hmp Index
MA.00473
Mitigation Actions Title
EMS 4 Flood Protection
Mitigation Actions Description
Raise utilities, wet floodproof building, raise generator on platform.
Lead Agency
Fire Department of the City of New York
Action Category
Property Protection
Action Status
In-Progress
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2019-05-31T00:00:00.000
Estimated Finish
2025-12-30T00:00:00.000
Estimated Cost
$2,500,000.00
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
FDNY Administrative Internal Priority
Financial Capability
Hazard Mitigation Grant Program (HMGP)
MA.00474
Hmp Index: MA.00474 • Mitigation Actions Title: Engine 202 Flood Protection • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00474
Mitigation Actions Title
Engine 202 Flood Protection
Mitigation Actions Description
Firehouse is located in zone AE and received 5' of water on the apparatus floor, plus the basement was flooded. Basemetn continually floods. Facility has a side yard and propose to house all utilities in an elevated watertight container.
Lead Agency
Fire Department of the City of New York
Action Category
Property Protection
Action Status
Proposed or Not Started
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms,Flooding
Estimated Start
2025-01-01T00:00:00.000
Estimated Finish
2026-01-01T00:00:00.000
Federal Funding Source
FEMA
Description Of Critical Facility
FDNY emergency response
Planning Regulation Capability
Hazard Mitigation Plan
Administrative Technical Capability
FDNY Administrative Internal Priority
Financial Capability
Hazard Mitigation Grant Program (HMGP)
MA.00476
Hmp Index: MA.00476 • Mitigation Actions Title: FDNY storehouse improvement • Lead Agency: Fire Department of the City of New York
Hmp Index
MA.00476
Mitigation Actions Title
FDNY storehouse improvement
Mitigation Actions Description
Expand and create additional storehouses that would assist in ensuring continuity of basic agency operations as well as response operations.
Lead Agency
Fire Department of the City of New York
Action Category
Property Protection
Action Status
Completed
Action Status Date
2023-12-15T00:00:00.000
Hazards Addressed
Coastal Storms
Estimated Start
2012-12-31T00:00:00.000
Estimated Finish
2015-12-30T00:00:00.000
Estimated Cost
$1,000,000.00
City Funding Source
City Capital
Description Of Critical Facility
FDNY emergency response
Administrative Technical Capability
FDNY Administrative Internal Priority
Notes
Storehouse built in the Navy Yard and Foster Avenue.